Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Repair Jira Macros

...

  1. Load the plugin library (MultipleScenarios.dll).

  2. Load the project.
  3. Load and configure all catchment and river system scenarios to be run.
  4. Click the "Associate Nodes" (left) icon on the main menu bar:



  5. A new window will appear that enables nodes to be associated:



    For each node pair you wish to associate:

    1. Select the outlet node in the first scenario (i.e. the node having a single upstream link) and click the "Set First Node" button;
    2. Select the inflow node in the second scenario (i.e. the node having a single downstream link) and click the "Set Second Node" button; and
    3. Click "Associate Nodes" to add the node associations to the list in the bottom panel.

    Notes:

    • A catchment node should have only one upstream link and a river inflow node should have only one downstream link. Once associated, the two nodes are effectively equivalent and modelled data from the catchment node is passed onto the inflow node.
    • This functionality may in the future be integrated into the "Reload on Run" functionality for "Scenario Data Source". See
      Jira Legacy
      serverSystem JIRA
      serverIdc4ca6e0fa22b5711-9f422728-3d1a3bcc-879c860f-870abe699ab12832d905a432
      keyRM-10186
      for more details.
    • Saving the project will save the node associations.

     

  6. Once all node associations are defined, the "Associate Nodes" window can be closed.

  7. Click the "Process Scenarios" (right) icon on the main menu bar:



  8. A window will appear showing the list of scenarios that have been configured and are ready to run:



  9. Click "Run Scenarios" to run all scenarios shown in the list.

    Notes:

    • Each scenario must be configured prior to it being run by the plugin.

    • The order in which scenarios are run is computed automatically based on the node associations.
    • All scenarios appearing in the list of scenarios are run sequentially without further user interaction. Results from all scenarios will be available in the recording manager. The results for the first nodes in the node associations will also be available as scenario data sources in the data manager.

  10. Once all scenarios are run, the "Process Scenarios" window can be closed.

...