- Trash racks (n = 17): average capital cost ≈ $966/ha; average annual maintenance cost ≈ $2,346; and average annual maintenance cost per ha ≈ $39.
- Large trash baskets (0.5 m3 m3 capacity) (n = 9): average capital cost ≈ $2,117/ha; average annual maintenance cost ≈ $708; and average annual maintenance cost per ha ≈ $42.
- Proprietary in-ground devices (n = 19), not including SEPTs: average capital cost ≈ $6,122/ha; average annual maintenance cost ≈ $765; and average annual maintenance cost per ha ≈ $156.
...
Walsh (2001) reported that the typical capital cost in Melbourne for vortex type in-ground GPTs that are operated by local government authorities was $100,000 per m3m3/sec (when the flow is at its peak treatment rate).
...
Melbourne Water (2003a) has a basic construction cost estimation model for large greenfield wetlands in Melbourne. It It allows for typical site characteristics to be used as factors that determine overall construction cost. The The cost relationships appear to be based on a limited data set (i.e. tender information for ~8 BMPs).
...
Fletcher et al. (2005) suggested that the construction cost of an infiltration trench is ~$60-80/m3 m3 of trench (assuming the trench is 1 m wide and 1 m deep).
...
Beecham (2002) estimated vegetated swale maintenance costs for Sydney conditions as $3.13/m2, based on the following unit rates: $1.62/100m2 for mowing (required 2 - 3 times a year), $16.20/100m2 for general grass care, $0.95/m2 for litter removal, $0.65/m2 for reseeding and fertilisation (1% of the total area is revegetated per year), and $1.35/m2 for m2 for annual inspections and administration.
A unit cost of $100 per linear metre was used for the construction of a road-side grassed swale during a desk-top water sensitive urban design project in the Snowy Monaro region (Lane, 2004). Roadside Roadside swales are typically 3m wide.
...
Leinster (2004) reported the following construction costs associated with bioretention systems in greenfield developments within South East Queensland:
- Bioretention systems greater than 100m
- Bioretention systems less than 100m
- Swale bioretention systems: $100 - 120/linear metre including vegetation (for this system the filter zone has a width of 1 m and the swale has a top width of 3-4 m).
The Centre for Watershed Protection (CWP, 1998) and US EPA (2001) reported the typical annual maintenance cost ≈ 5-7% of the construction cost.
...
Table 1. Cost estimates associated with aquaplate above ground tanks
Item | Approximate cost for each tank size (in $2001) | ||
---|---|---|---|
5kL | 10kL | 15kL | |
Aquaplate rainwater tank | 540 | 870 | 1200 |
Pump + pressure controller | 200 + 160 | 200 + 160 | 200 + 160 |
Plumber and fittings | 500 | 500 | 500 |
Float system | 100 | 100 | 100 |
Concrete base | 200 | 200 | 200 |
GST (10%) | 170 | 200 | 240 |
Total (incl. GST) | $1,910 | $2,230 | $2,600 |
- pumps typically have a 10 year life span; and
- the operating and maintenance cost of pumps are approximately $0.1 per kL of rainwater consumed. (Note that a typical family home may use ~20 kL/year of water for toilet flushing.)
Table 2. Cost estimates for supply and installation of above and below ground rainwater tanks or a single installation in Sydney
Tank size | Tank type | Tank shape | Approximate tank supply cost |
---|---|---|---|
1.5kL | Galvanised steel, aboveground | Round Rectangular / ovular | $2,470 $2,870 |
...
Colorbond finish with a polymer type liner, aboveground | Round Rectangular / ovular | $2,570 $2,970 | |
3kL | Galvanised steel, aboveground | Round Rectangular / ovular | $2,970 $3,470 |
...
Colorbond finish with a polymer type liner, aboveground | Round Rectangular / ovular | $3,320 $3,820 | |
5kL | Galvanised steel, aboveground | Round Rectangular / ovular | $3,170 $4,280 |
...
Colorbond finish with a polymer type liner, aboveground | Round Rectangular / ovular | $3,620 $4,600 | |
9kL | Galvanised steel, aboveground | Round | $3670 |
...
Colorbond finish with a polymer type liner, aboveground | Round | $4,120 | |
5kL | Below ground (Rocla Eco Rain) | - | $7,800 (plus $800 for reticulation to toilets) |
10kL | Below ground (Rocla Eco Rain) | - | $11,050 (plus $1,050 for reticulation to toilets) |
Table 3. Prices for polyethylene (plastic) rainwater tanks
Tank size (L) | Tank type | Approximate tank supply cost ($) |
---|---|---|
509 | Slim line (aboveground) | $491 |
700 | Tall round (aboveground) | $418 |
720 | Slim (aboveground) | $501 |
758 | Round (aboveground) | $511 |
1,074 | Slim (aboveground) | $766 |
1,179 | Round (aboveground) | $521 |
1,250 | Round (aboveground) | $550 |
1,400 | Tall slim (aboveground) | $792 |
1,615 | Round (aboveground) | $551 |
1,800 | Under house (aboveground) | $1,122 |
2,100 | Tall slim (aboveground) | $1,144 |
2,281 | Slim (aboveground) | $1,271 |
2,499 | Squat (aboveground) | $601 |
2,500 | Round (aboveground) | $682 |
2,500 | Twin under-deck (aboveground) | $1,122 |
2,542 | Tall (aboveground) | $601 |
2,800 | Tall slim (aboveground) | $1,496 |
3,600 | Twin rectangular under house (aboveground) | $2,244 |
4,125 | Squat (aboveground) | $901 |
4,885 | Medium round (aboveground) | $901 |
5,000 | Round (aboveground) | $968 |
9,000 | RT poly tank (aboveground) | $1,595 |
9,609 | Large squat (aboveground) | $1,850 |
10,478 | Large tall (aboveground) | $1,500 |
10,500 | RT poly tank (aboveground) | $1,705 |
13,500 | RT poly tank (aboveground) | $2,024 |
15,064 | Large (aboveground) | $1,850 |
22,500 | Low profile (aboveground) | $2,376 |
22,500 | RT poly tank (aboveground) | $2,640 |
24,180 | Large tall (aboveground) | $2,551 |
25,090 | Large low profile (aboveground) | $2,551 |
29,560 | Very large (aboveground) | $2,950 |
38,334 | Very large (aboveground) | $4,170 |
47,950 | Monster (aboveground) | $5,152 |
Grant and Hallmann (2003) estimated the costs associated with a 2,250 litre plastic tank with a life span of 30 years as: $510 purchase; $38.50 (delivery); $270 (for plumbing costs that allow toilet flushing and garden watering to use tank water); $350 (for the pump); $100 (electrician costs). They also assumed the pump would last for 15 years, and the cost of running the pump (in Melbourne) was estimated to be $0.1368/kwh.
Additional costs and Cost break-downs
References
...
...
...
Booklet 1: Project Cost Summaries and Workshop Information’ (Gibbs, S., Ed.). Booklet for the ‘How Much Does WSUD Really Cost?" workshop in Newcastle, 1 July
2003. Lower Hunter and Central Coast Regional Environmental Management Strategy, Newcastle, New South Wales.
...
...
...
...
Booklet for the ‘How Much Does WSUD Really Cost?" workshop in Newcastle, 1 July 2003. Lower Hunter and Central Coast Regional Environmental Management
Strategy, Newcastle, New South Wales.
...
...
Cost? Booklet 1: Project Cost Summaries and Workshop Information’ (Gibbs, S., Ed.). Booklet for the ‘How Much Does WSUD Really Cost?" workshop in Newcastle,
1 July 2003. Lower Hunter and Central Coast Regional Environmental Management Strategy, Newcastle, New South Wales.
...
...
...
Coombes, P. (2002). Practice Note No. 4 - Rainwater Tanks. Lower Hunter and Central Coast Regional Environmental Management Strategy, Newcastle, New South
Wales.
...
...
Technical Report 04/8. Cooperative Research Centre for Catchment Hydrology, Melbourne, Victoria.
...
...
...
...
Conference. Brisbane, September 2003.
...
Information. Booklet for the ‘How Much Does WSUD Really Cost?" workshop in Newcastle, 1 July 2003. Lower Hunter and Central Coast Regional Environmental
Management Strategy, Newcastle, New South Wales.
...
...
...
...
costing survey of Australian stormwater managers.
...
Council.
...
...
...
...
Association 2001 Regional Conference. Port Stephens, New South Wales, 26-28 April 2001.
...
Shoalhaven, New South Wales.
...
...
...
Cooperative Research Centre for Freshwater Ecology, Melbourne, Victoria. Referenced heavily in Fletcher et al. (2005).
...
...
...
...
...
...
Civil, Rozelle Bay, New South Wales.
...
governments.
...
...
Developments - How Much Does WSUD Really Cost? Booklet 1: Project Cost Summaries and Workshop Information’ (Gibbs, S., Ed.). Booklet for the ‘How Much
Does WSUD Really Cost?" workshop in Newcastle, 1 July 2003. Lower Hunter and Central Coast Regional Environmental Management Strategy, Newcastle, New
South Wales.
...
...
Centre for Catchment Hydrology, Melbourne, Victoria. Available at: https://www.
...
...
...
Technical Report 02/13, Cooperative Research Centre for Catchment Hydrology, Melbourne, Victoria. Available at:
...
...
...
Environmental Protection Agency on-line guideline: www.epa.gov/npdes/menuofbmps/menu.htm (August 2004).
...
New South Wales.
...
...
Department of Transportation, Washington.
...
...
URS (2003).Weber, T. (2001) & (2002). Tony Weber, Senior Waterways Program Officer (Water Quality), Brisbane City Council, Queensland, personal communication.
Cited in Taylor and Wong (2002).
...
...
cost and typical annual maintenance cost. For more information see Taylor (2003). Also, these approximate costs will vary with time and location. For up-to-date costs
of proprietary units, contact the GPT supplier.
[2]
...
...