- Right click Rating Curve and choose Add Rating Curve;
- Today’s date will automatically be entered for Start Date. To change this, click the calendar on the right side (see Working with date-pickers);
- Enter the water level, discharge rate, reach width and dead storage; and
- Enter an appropriate value for Overbank Flow Level.
Jira Legacy showSummary false server System JIRA serverId c4ca6e0fa22b5711-9f422728-3d1a3bcc-879c860f-870abe699ab12832d905a432 key RM-14731
Figure 4. Storage routing link, Rating curve
...