Introduction
Operations forecasting allows you to create alternate forecasts for inflows, water demands, stream flow losses and gains (unaccounted differences) and constituents within a single overall project scenario. In other words, it forecasts the input data for a model. This is not available in Source (public version).
...
- First, create a schematic scenario;
- Choose Tools » River Operations to open the River Operations dialog (Figure 1); and
- Click on the slider below Operations Mode to ON.
Once you have created forecast models, you can disable operations, but retain these models or overrides using the buttons under Operations Data. The first two buttons in this dialog deal with removing input data, whereas the third one deletes all output data that was created for the forecast models. To clear all operations related data (input, output as a well as overrides), click Clear ALL Operations Data.
Figure 1. River Operations
Anchor | ||||
---|---|---|---|---|
|
Before you can begin forecasting, you must seed the model with available historical data (also known as "warming-up the model") using the Simulation toolbar:
...
This opens the Run w/Warm Up dialog (Figure 2).
Figure 2. Run w/Warm Up
Assuming a daily time-step:
...
The Constituents tab gets enabled when constituents have been configured in a scenario (its operation is similar to the Constituents tab in a single analysis run).
Anchor | ||||
---|---|---|---|---|
|
Once operations has been enabled, you can configure forecast input data under the relevant forecasting list item in a node's feature editor. For example, for the inflow node, choose Inflow Forecast under Additional Flow. Each of the parameters that are involved in creating forecasts handle input data differently.
...
For gauged releases forecast at the storage node, by default, the modelled releases are used by outlets, except where an override value has been provided, either by direct override (using the tabular editor) or by a forecast model. A storage outlet is a physical structure which has minimum and maximum release capabilities. The outlet release forecast/override can be any value, but the model cannot physically release any amount. The forecast/override values are therefore constrained at run-time. This is why the outlet releases each have two columns in the tabular editor, the first shows the modelled value that is actually released by the storage and the second shows the forecast/override. They will be different if the outlet release has been constrained. The second column is blank in the absence of any forecast/override values and in this case, the modelled values are used. Figure 3 shows an example of this. Note that from the 01/02/2011 onwards, the outlet release has been constrained.
Figure 3. Tabular Editor, forecasting, outlet release constrained
Forecast scenarios
Anchor | ||||
---|---|---|---|---|
|
A collection of one or more forecasting models is known as a forecast scenario. You can define one or more scenarios for each node. For example, you might define "wet year", "dry year" and "normal year" scenarios, or variations that reflect your most optimistic or pessimistic expectations. To add a forecast scenario, right-click on the item you want to forecast in the relevant node's feature editor and choose Add Forecast Scenario (Figure 4). You can choose the input set that will be associated with a particular forecast scenario. Right click on Forecast Scenario #<number>, then choose Add Forecast Model to add a model.
...
Figure 4 shows the Forecast item for the Inflow node. Choose the forecast model you wish to specify by clicking the appropriate forecast model under Additional Flow Forecast (on the right). The forecast model that is active at the node is indicated by a green tick on the left of the model. In Figure 4, the Trend forecast model is the active model.
Figure 4. Inflow node, Operations forecasting
Figure 5. Storage Routing Link, Operations forecasting
Info | ||
---|---|---|
| ||
Note: Forecast scenarios are unique to a node and must be configured individually for each node. |
Forecasting models
Source supports the forecasting model types shown in Table 1.
Table 1. Forecast model types
Forecast model type | Description |
---|---|
Average | Allows you to define the average over the last specified number of time-steps. |
Function | Allows you to define an expression or define a function to return any value you choose for each time-step in the forecast period. For example:
|
Monthly Average | Allows you to enter an average forecast value, in megalitres per day, to be applied for the whole of each month. You can either enter the monthly average values manually, or import the values from a .CSV file formatted as shown in Table 2. To trend from "today" to the monthly average, enable the Trend to Value at Rate checkbox and enter a trend rate which is a real number greater than zero but less than one. The observed daily flow rate for the previous month and the number of days of the current month are used to determine the initial flow volume. |
Pulse | Allows a static forecast model that is applied on a specified date and has priority over other relative forecast models if enabled. The forecast pulse flow rate is entered under the Target Flow configuration, and the pulse start and end dates are specified with the date inputs. The rate of the rise and recession of the pulse is configured by the Rate sliders or can be entered directly as value. For example, the 0.6 Rate of the Pulse Rising indicates that at each time step there is an increase of 60% in the flow volume until the Target Flow is reached.. |
Time Series | To specify a forecast based on a time series, you must:
Time series are assumed to conform with the structure shown in Table 3. Note that any time-stamps contained in a time series are ignored. The observation in the first row of the time series is used for the first time-step of the forecast period, the observation in the second row for the second time-step, and so on, until either there are no more data rows in the time series or the simulation reaches the end of the forecast period. |
Trend | A single target value (either positive or negative) plus a recession rate. To specify a trend forecast, enter the target value in megalitres per day, and use the slider to specify the trend rate, which is a real number greater than zero but less than one. |
Figure 6. Pulse Forecast Model
Table 2. Monthly average forecasting model (data file format)
Row | Column (comma-separated) | |
---|---|---|
1 | 2 | |
1 | Month | Forecast Value (ML/d) |
2..n | month | value |
Table 3. Time series forecasting model (data file format)
Row | Column (comma-separated) | |
---|---|---|
1 | 2 | |
1..n | date | value |
Viewing forecasts
The results of executing one or more forecast scenarios can be viewed using the Recording Manager or the tabular editor (to view and override individual values). Ensure that you enabled recording for the parameter that you are forecasting. For example, to forecast flow, enable recording of the Inflow attribute in the Recording Manager. Figure 5 shows an example of the output of a forecasted model. This forecasting scenario consists of two forecast models. A Trend forecast model is run for the first 10 time-steps and the remaining time-steps have a Function forecast model configured.
Figure
...
7. Charting tool, forecast models
...