Introduction

Linear programming techniques assume that the data used is perfect. In particular, when activating these features, you are assuming that the objective function and constraint coefficients are correct, rather than the best estimates available. If this assumption does not hold, the solutions found may be sub-optimal.

...

*side constraints have not yet been fully implemented and tested in Source

Anchor
ConfiguringOptimisation
ConfiguringOptimisation
Configuring optimisation

To configure optimised ordering, begin by choosing Edit » Ordering » Network Costs... or click Configure Ordering on the Ordering toolbar and choose Network Costs.... This opens the Network costs dialog (Figure 1).

Figure 1. Network costs (summary)

Image RemovedImage Added

Creating cost functions

...

Figure 2. Network Costs (Storage Break Points)

Image RemovedImage Added

Note
Although you can define storage breakpoints for storage A in terms of storage B, you should avoid doing so because it can lead to infeasible solutions.

...

A more formal specification of the cost calculation is:

Equation 1
Image RemovedImage Added

Recall that negative costs are incentives. Accordingly, in this table, the greatest incentive is to retain any water in the bottom-most 10% of the capacity of the storage (for carry-over to the next time-step), followed by the water in the next 40% of the capacity of the storage. By interleaving base costs and increment values, releases from multiple storages can be controlled quite precisely to maintain a desired balance.

...

Figure 3. Carryover Arc Costs vs Storage Volume

Image RemovedImage Added

Applying cost functions

...

Figure 4. Network costs (Storage targets)

Image RemovedImage Added

You can also import storage targets from a .CSV file. The format of the file is shown in Table 3. Note that the column ordering in the .CSV file does not match the display in Figure 4.

...

Figure 5. Network  costs (Demand priorities)

Image RemovedImage Added

You can control the order in which shortfalls are satisfied. The Priority column in Figure 5 shows which demand component of the model has will receive water via its shortfall arcs.

...

Info
iconfalse
Note: In a netLP system, refer to Operating targets when setting up a storage node.

...

Troubleshooting It is possible to visualise the arc-node networks that are generated by Source using third party software. For more information please see: Troubleshooting and Debugging